cr_42_edited_penny_tax.jpg

PENNY

sales tax

Road Projects

2017-2020

aerial view of Nortwest 49th/35th Street phase 2b and 2c

Northwest 49th/35th Street Phase 2B and 2C

A new four-lane roadway from Northwest 44th Avenue to the Ocala city limits, including an interchange at I-75. This will provide traffic-carrying capacity and enhance the opportunity for economic development in the area.

  • Cost: $47,000,000

  • Sales Tax Funding $26,575,000

  • Length: 1.2mi 

  • Status: In Progress

aerial of Southwest 49th/40th Avenue phase 1, 2 and 3

Southwest 49th/40th Ave
Phase 1, 1A, 2, 3

A four-phased project that includes a new four-lane from Southwest 95th Street to Southwest 42nd Street, boosting traffic capacity.

  • Cost: $20,431,120

  • Sales Tax Funding $12,297,849

  • Length: 5mi 

  • Status: In Progress

17_SW49THAVEPHASE1__1536610684108__w1056

Southwest 49th Avenue South
Segments A & E

A new four-lane roadway from 1.1 mile south of Hwy 484 to Marion Oaks Trail. This project is another phase of SW 49th Avenue corridor.

  • Cost: $11,060,000

  • Sales Tax Funding $11,060,000

  • Length: 1.5mi 

  • Status: In Progress

satellite view of Northeast Highway 315

Northeast County Road 315

Rehabilitation from County Road 316 to County Road 318.

  • Cost: $5,074,391

  • Sales Tax Funding $5,074,391

  • Length: 9.9mi

  • Status: Complete

16_COUNTYROAD484__1536610444452__w1056.j

County Road 484

Adding two lanes to Highway 484 from Marion Oaks Pass to Marion Oaks Course, improving traffic capacity and flow along this congested corridor.

  • Cost: $8,900,000

  • Sales Tax Funding $8,900,000

  • Length: 1.5mi 

  • Status: In Progress

Northwest Gainesville Road   (C.R. 25A)

Rehabilitation from County Road 329 to US 441

  • Cost: $3,088,885

  • Sales Tax Funding $3,088,885

  • Length: 5.2mi

  • Status: Complete

satellite map of County Road 464B

County Road 464B

Rehabilitation from the Levy County line to U.S. Hwy 27

  • Cost: $3,316,071

  • Sales Tax Funding $3,316,071

  • Length: 7.1mi

  • Status: Complete

satellite view of South Highway 314A

South Highway 314A

Rehabilitation from Southeast 95th Street Road to Southeast 24th Street Road

  • Cost: $3,300,000

  • Sales Tax Funding $3,300,000

  • Length: 5.5mi

  • Status: In Progress

satellite view of Southeast 182nd Avenue Road

Southeast 182nd Avenue Road

Rehabilitation from County Road 42 to Southeast 95th Street Road

  • Cost: $3,111,088

  • Sales Tax Funding $3,111,088

  • Length: 7.6mi

  • Status: Complete

satellite view of Marion Oaks Boulevard

Marion Oaks Boulevard

Rehabilitation from Marion Oaks Manor between 56th Terrace Road and 56th Court to Marion Oaks Manor between 31st Court and SW 29th Court Road

  • Cost: $1,722,823

  • Sales Tax Funding $1,722,823

  • Length: 3.7mi

  • Status: Complete

satellite view of County Road 316

County Road 316

Rehabilitation from County Road 315 to west of the Eureka Bridge 

  • Cost: $2,315,171

  • Sales Tax Funding $2,315,171

  • Length: 4mi

  • Status: Complete

satellite view of County Road 326

County Road 326

Rehabilitation from the Levy County line to U.S. Highway 27.

  • Cost: $2,095,189

  • Sales Tax Funding $2,095,189

  • Length: 4.1mi

  • Status: Complete

satellite of County Road 42

County Road 42

Rehabilitation from U.S. Highway 441 to County Road 25.

  • Cost: $1,500,000

  • Sales Tax Funding $275,859

  • Length: 3.7mi

  • Status: Complete

Emerald Road

Emerald Road

Rehabilitation from Maricamp Road southwest to Oak Road.

  • Cost: $441,676

  • Sales Tax Funding $441,676

  • Length: 1.1mi

  • Status: Complete

satellite of County Road 320

County Road 320

Rehabilitation from I-75 to U.S. Highway 441.

  • Cost: $1,037,133

  • Sales Tax Funding $1,037,133

  • Length: 2.8mi

  • Status: Complete

Southwst 107th Place/County Road 475B

Southwest 107th Place (CR475B)

Rehabilitation from County Road 475A to County Road 475.

  • Cost: $575,168

  • Sales Tax Funding $575,168

  • Length: 1.1mi

  • Status: Complete

Southwest 38th Avenue

Rehabilitation from Southwest 95th Street to Southwest 66th Street

  • Cost: $813,394

  • Sales Tax Funding $813,394

  • Length: 3.11mi

  • Status: Complete

Emerald Road Extension

A new two-lane roadway from SE 92nd Loop to the existing terminus at Florida Northern Railroad.

This will create a continuous corridor from east Maricamp Road to SE 92nd Loop.

Besides adding traffic-carrying capacity for southeastern Marion County and Silver Springs Shores, this new corridor will provide relief to the intersection of SE Maricamp Road and SE 58th Avenue. 

  • Cost: $11,097,945

  • Sales Tax Funding $409,622

  • Length: 1.8mi

  • Status: In Progress

NW 80th Ave / 70th Ave Rd.

Design phase to add two lanes to NW 80th Ave/70th Ave Rd. from SR40 to 0.5mi north of US 27.

  • Cost: $2,297,963

  • Sales Tax Funding $2,297,963

  • Length: 4.2mi

  • Status: In Progress

NW/SW 80th Ave at Hwy 40

Road widening from 1300ft south of Hwy 40 to 1500ft north of Hwy 40, with signalization added at Hwy 40. 

  • Cost: $5,350,000

  • Sales Tax Funding $5,350,000

  • Length: 0.8mi

  • Status: In Progress

NW 70th Avenue at US 27

Road widening from 1300ft south of US 27 to 1500ft north of US 27, with signalization added at US 27.

  • Cost: $6,710,000

  • Sales Tax Funding $6,710,000

  • Length: 0.78mi

  • Status: In Progress